Banks won’t budge on road loan riders

October 15, 2013

Timsy Jaipuria, Arun S | New Delhi |
 
 

Many banks have virtually stopped lending to road projects where the developers are unable to bring 50% equity capital upfront, do not have 100% of the required land in possession or have not obtained the requisite environmental clearances.”We have been insisting on these two requirements (100% land and 50% equity capital upfront by promoters) for quite sometime now,” a senior Punjab National Bank official told FE, wishing not to be quoted.Sources in the road sector and the National Highway Authority of India (NHAI) also confirmed that despite several meetings with NHAI and the road ministry, banks have started asking highway developers to show more equity contribution upfront before they lend to the project.

SBI, another big player in the area, has discontinued lending to road projects without 100% land in possession.

RK Dubey, chairman and managing director (CMD) of Canara Bank, said though the bank has not brought out general guidelines internally, it is getting selective when in lending to road projects. “Since we can’t choke funds to the sector, we have strengthened our due diligence process. We are giving loans only on the basis of the financial strength of the group that is developing the project. We have to safeguard the interest of our bank in all the possible ways as the non-performing assets are rising,” he said.

M Narendra, CMD of Indian Overseas Bank, said banks have started a stringent scrutiny of the concession agreement, besides looking at annuity payments, toll projections of the project during the entire concession period and whether there are any pending legal hurdles in the land acquisition process.

Arun Kaul, CMD of UCO Bank, said his bank has decided to go slow on infrastructure projects, including road projects, and rebalance its portfolio, which was earlier heavily skewed towards infrastructure and large corporates.

“From 75-76% of the total lending to infrastructure and large companies and only the remaining in retail and SME lending three years ago, we have rebalanced, and brought it down to 50% for each segment by focusing heavily on retail and SME loans using our branch network and technology,” Kaul said.

“In the last three years, we have not taken on any road project and have become highly selective when it comes to such projects due to the stress in the economy and the problems faced by companies in that sector,” he added.

The Centre for Monitoring Indian Economy in a report last month said, “66 highways and road projects worth R1 trillion (R1 lakh crore) are facing delays or have not taken off due to problems related to land acquisition.”

“Out of these, 44 projects worth R936 billion (R93,600 crore) are promoted by the NHAI. Only two of the total 66 projects have received environmental clearance,” it added.

An NHAI official said: “The lenders are following a very cautious approach towards the road sector since the players are over-leveraged. Banks are not sure whether they would be able to get back their money. They have started asking the developer to show the equity capital upfront and are questioning where that equity money is parked at present. This is the first time that lenders are doing this. It’s causing private players trouble .”

Recently, Oscar fernandes, in an interview to FE, had noted: “The basic thing is unless the concessionaire brings in his capital the project can’t take off. If the developer depends on borrowed money for the whole of the project’s requirement, then why do we need him? If that is the case, then we (NHAI) can fund the project and recover the money on our own.”

“We seek partnership with private firms in the belief that they will bring equity, that is, initial capital. What happens in some cases is that the developers borrow on the basis of toll collections, which means they take no risk. Which concessionaire would give his personal property and guarantee to the bank before borrowing?” he said.

Gross bank credit outstanding to the sector as on March 22, 2013 was R1,31,300 crore, says RBI data.

 

Source-http://www.financialexpress.com

 

 

Bankers launch initiative to get stalled infra projects moving

March 29, 2013

Bankers launch initiative to get stalled infra projects moving

K. RAM KUMAR

Awaiting push: Development of adequate and quality infrastructure is a necessary condition to maintain growth momentum in any economy
Awaiting push: Development of adequate and quality infrastructure is a necessary condition to maintain growth momentum in any economy
MUMBAI, MARCH 27:

The wheels of the Government seem to be turning to get new and stalled projects in the power, road, iron and steel, cement, and port sectors off the ground.

Following Finance Minister P. Chidambaram’s meeting with the chiefs of public sector banks (PSBs) and state-owned financial institutions on March 18, the process of region-wise stock-taking of new and stalled projects has begun.

The first meeting, organised by Canara Bank, was held in Bangalore last week. Top representatives of major banks headquartered in the South, their large clients having projects in the region and top Finance Ministry officials were present at the meeting.

Similar meetings would be held in Delhi, Mumbai and Kolkata.

GDP AND INFRASTRUCTURE

The stock-taking initiative on new and stalled projects comes at a time when growth has decelerated significantly. India’s GDP growth at 4.5 per cent, in the October-December quarter of 2012-13, was the weakest in the last 15 quarters.

According to Reserve Bank of India Deputy Governor H.R. Khan, infrastructure development facilitates economic growth and economic growth in turn increases demand for more infrastructure. Thus, development of adequate and quality infrastructure is a necessary condition, if not sufficient, to maintain growth momentum in any economy.

Finance Ministry estimates show that there are 215 projects, each with a project size of Rs 250 crore and above, that are stalled. Out of 215 projects, 106 are in the power sector, 79 in roads, 20 in iron and steel, and 5 each in cement and port sectors.

All these projects, which collectively involve an outlay of over Rs 7 lakh crore, have been supported by PSBs. As at December-end 2012, PSBs had disbursed Rs 54,000 crore to the projects.

Delays in land acquisition, resettlement and rehabilitation issues, environmental clearances, tie-up of project financing, non-availability of fuel for power generation, lack of infrastructure support and linkages are some of the reasons for the projects being stalled.

During the current financial year up to December 2012, PSBs received 126 new projects — in power, power, road, iron and steel, cement, and port sectors — involving a collective outlay of Rs 3,55,880 crore. The projects are at various stages of appraisal and sanction.

ADDRESSING BOTTLENECKS

At the March 18th meeting, Government officials sought to assure bankers that the issues relating to coal linkages are getting addressed with bids being called for new projects.

Delays associated with environmental clearance are also likely to be sorted out shortly with the proposal to de-link forest clearance from environment clearance and an agreement being reached between various Ministries to expedite the clearance process.

Most of the issues relating to highway projects were being addressed and there is a likelihood of the various roadblocks being duly addressed by the Cabinet Committee on Investment. Issues relating to 37 road projects, where the selected promoters were not performing, would also be addressed shortly.

As regards electricity distribution companies, issues with related to settlement on the interest rate (on outstanding loans) to be charged are likely to be resolved.

AREAS OF CONCERN

Iron ore mining was still stuck in the courts and it was not clear when this issue would be addressed.

Gas supply for power projects remains a concern.

In the case of road projects, huge funds are stuck in arbitration. Hence, bankers want the Finance Ministry to intervene and impress upon the National Highways Authority of India to settle these cases out of court at the earliest so that funds could be released into the system.

Escalation in project costs due to time and cost overruns is likely to raise problems for banks.

[email protected]

 

 

Source-http://www.thehindubusinessline.com