Postal highway project in limbo
October 9, 2013
Warning: Undefined variable $thumb in /var/www/web/indiantollways.com/wp-content/plugins/digg-digg/include/dd-class.php on line 887
SURESH YADAV
JANAKPUR, : Eight access roads that Nepal and India had agreed to complete in the Tarai this year under the postal highway project have completely fallen by the wayside.
According to a bilateral agreement inked around three years back eight access roads were to be constructed in Dhanusa, Mahotari and Sarlahi districts by this November 12. But only Birendrabazar-Mahinathpur road in Dhanusa is under construction.
India had released more than Rs 2.5 billion for the project 29 months ago.
A meeting was held in Janakpur a few days back to discuss the factors leading to the delay.
Indian ambassador Ranjeet Rae, who attended the meeting, held the construction companies and the government of Nepal responsible for the tardy pace of the project.
“Had the government of Nepal handed over the task to the construction companies and the contractors had taken their responsibility seriously, the work would have already completed by now,” said Rae.
International companies such as Vishma, Wivi and SR Joint Venture had bagged the tenders for the project.
Chief at Janakpur Division Office of the postal highway project, Kishore Roy blamed Nepal Electricity Authority (NEA) and the Department of Forests.
“Even though we allocated the budget to remove electrical poles and trees along the road sections, NEA didn´t take the work seriously,” he said. “Moreover, had the construction companies started the construction immediately after the agreement, the progress would have been satisfactory.”
The project includes the construction of the access roads of Janakpur-Jatahi (12.06 km), Janakpur-Yadukuha (17.05 km), Janakpur-Jaleshwore-Vitamode (19.75 km), and Birendrabazar-Yadukuwa-Mahinathpur (32.35 km) in Dhanusa.
Maisthan-Gausala-Sashi (26.90 Km) and Jaleshowore-Hardikhola (27.20 km) in Mahotari, and Nayaroad-Barhathwa-Madhubani (40.31 Km) and Nawalpur-Mangalwa (26.59 km) road sections in Sarlahi are the remaining access roads to be constructed under the postal highway project.
Source-http://www.myrepublica.com