Lack of clearances delays infrastructure projects

October 16, 2013


Warning: Undefined variable $thumb in /var/www/web/indiantollways.com/wp-content/plugins/digg-digg/include/dd-class.php on line 887

Pavan MV,  TNN |

 

BANGALORE : Inspection of ongoing infrastructure projects is springing surprises at every turn , with decision makers finding that basic approvals haven’t been sought.On Tuesday , Bangalore development minister R Ramalinga Reddy found that the BDA requires 3.2 acrestocomplete the Nayandahalli flyover near Mysore Road which has been hanging fire for two years .Shockingly , the BDA commenced construction without completing land acquisition . The construction of the 960-metre long flyover began in 2010 and was scheduled to be completed by 2013 . Even if BDA gets the required land now , it needs five months to completethe project .Theland belongs to over 40 people .

Last week, during the inspection of the Road Over Bridge near Byappanahalli , mayor Sathyanarayana found that BBMP had commenced work on two ROBs at Byappanahalli and Jakkur without completing land acquisition .

The delay in the Nayanhahalli flyover has become a huge problem for commuters on Mysore Road due to frequent traffic jams . Alongside , work on the Metro rail is on and is adding to the gridlock .

Ramalinga Reddy said , “Since the property is situated on Mysore Road , its value is quite high and the owners expectusto pay the market value . We’ll sort out the issue soon .”

Metro corridor

After inspecting the Metro corridor work , Ramalinga Reddy said the National College Metro corridor will be completed by March 2014, and the train will run from Byappanahalli station to Mysore Roadstation by 2014.He also assured that Metro services from Peenya to Malleswaram would be operational by this year-end and work from Kaggalipura to City Market will be completed by 2015.

Pradeep Singh Kharola , MD, BMRC, said there is a proposal to concretize the road below the Metro corridor from MG Road station to Byappanahalli station . Asked about bad roads below the Metro corridors , he said road work cannot be taken up till Metro work is on .

On parking

BBMP is gearing up to provide parking for Metro commuters. BS Sathyanarayana said BBMP will identity properties belonging to it near all Metro stations. “Ramalinga Reddy has told us to utilize funds under the Jawaharlal Nehru National Urban Renewal Mission scheme for this project,” he said.