Four-laning of Hyderabad-Vijayawada road from December
April 7, 2008
Warning: Undefined variable $thumb in /var/www/web/indiantollways.com/wp-content/plugins/digg-digg/include/dd-class.php on line 887
VIJAYAWADA: The long-awaited Rs 1460 crore four-laning of Hyderabad-Vijayawada Road will commence in December. The National Highway Authority of India (NHAI) will finalise the tenders by June.
Currently, the four-laning has been completed between Vijayawada and Nandigama (50 km) and Hyderabad and Malkapuram (40 km). The 181 km stretch between Malkapuram and Nandigama will now be four-laned.
NHAI Vijayawada-Hyderabad section project director P Srinivasa Rao said the work will be completed in two years time. The NHAI, the State Government and the contractors will enter into a state-support agreement before commencing the works, he added.
VIJAYAWADA-MACHILIPATNAM ROAD: Srinivasa Rao said the the Vijayawada-Machilipatnam Road will also be widened to 200 feet. This would be done for 150 km. The tenders would be finalised in June and the works would begin from December.
The widening is estimated to cost Rs 493 crore. The widening has become necessary in view of the heavy vehicular movement on the road and the future needs that may arise after the establishment of the new port.
The project director met superintendent engineer of Irrigation T Shivaji recently to discuss the widening as some irrigation canals pass along the road.
Source: newindpress.com