NHAI yet to set target for BOT projects
April 29, 2013
By YASHODHARA DASGUPTA, ET Bureau | 29 Apr, 2013, 05.00AM IST
Road ministry fixes 9,000 Km national highway target for this fiscal
April 18, 2013
NEW DELHI: The road ministry plans to award at least 7,300 kilometres of national highways this financial year. It has fixed an internal target of 9,000 km, which is a tad more ambitious than last year’s revised target of 8,800 kilometres.
The ministry has set a target of awarding 3,800 km in the first six months itself – higher than the 3,000 km announced by thefinance minister in his budget speech in February. The decision was taken after a review meeting held today by the road minister C P Joshi.
“We have set high internal targets so that we are able to achieve at least 3,000-km in the first six months and 7,300 km by the end of the year,” a road ministry official told ET. Last year, the ministry had managed to award road projects for only 1,933 km – 20% of what was planned for 2012-13. This year’s target of 7,300 km is line with the government’s promise of building 20 km a day.
“Of the 3,800 km, 1,654 km will be awarded by the ministry, 2,147 km will be through NHAI, about 1,200-km via the Engineering Procurement and Construction mode and 1,400 km through the Build-Operate-Transfer model,” said the official.
The road sector saw a dramatic drop last year in the number of projects that were bid for by companies. As many as 13 projects worth about 16,000 crore saw no takers. In contrast, 6,644-km – the highest since 2004 – was awarded in 2011-12. Ministry officials attribute this to a lack of equity with road construction companies and the overall economic environment. Given the subdued response to BOT toll projects, the ministry now plans to award more than 50% of the projects through the Engineering Procurement Construction mode.
It also aims to complete 4,500 km this year under schemes of National Highway Development Programme, Special Accelerated Road Development Programme for the North-East and Left Wing Extremism affected regions.
http://economictimes.indiatimes.com
NHAI pushes for removal of Gurgaon toll plaza
April 18, 2013
“This arrangement would mean large number of vehicles plying between Gurgaon and Delhi won’t be subjected to traffic snarls and won’t have to pay toll. On the other hand, the traffic towards Jaipur would pay full toll at a single point outside Gurgaon,” said the official.
Sources said the nitty-gritty of the arrangement are yet to be worked out. These would be proposed by the project’s lender and concessionaire. They added that at present around Rs 18 crore per month is collected as toll from both plazas on the expressway — roughly Rs 12 crore at the 32-lane toll plaza and Rs 6 crore at km 42 toll plaza. In case the first plaza is done away with, the overall toll collection would fall to Rs 10 crore, which would make the plan financially viable for concessionaire Delhi-Gurgaon Super Connectivity Ltd (DGSCL) and the lead lender, Infrastructure Finance Development Company.
DGSCL had taken a loan of Rs 1,567 crore from a consortium of banks led by IDFC for this project. Officials familiar with the development said recovering this net present value (NPV) of the project from a single toll plaza would be impossible. If the plan to remove the 32-lane plaza goes ahead, both the lender and the concessionaire would have to take a financial hit.
In this case, the Haryana government could step in to compensate the project operator and lender. Chief minister Bhupinder Singh Hooda had shown interest last November in “purchasing” the project to make expressway travel hassle free. This would also suit his government in an election year, considering the huge public demand to remove the toll plaza and treat the expressway as an urban road connecting two cities.
These talks are on even as all the three parties – NHAI, IDFC and DGSCL – have filed cases against each other in the Delhi High Court. In the last hearing, IDFC had sought time from the court to put forward a settlement proposal. The court had allowed all parties to come out with a settlement and had fixed the next date for hearing to May 2.
Building 20 km highways per day a long way off
April 1, 2013
Building 20 km highways per day a long way off
NEW DELHI: Building 20 km of road on national highways a day is still a distant dream for the UPA II government.
Four years after the then road minister Kamal Nath had announced the ambitious target, the National Highways Authority of India — the central agency which builds highways across the country – has managed to build just 8 km of highways per day during the financial year 2012-13 that ended on Sunday.
According to statistics made available by the NHAI, the agency was able to construct a little over 2900-km stretch in 2012-13. Though the figure is highest so far (see box), NHAI still has way to go before it is able to meet the 20-km-a-day target. To achieve this, NHAI will not only have to award higher number of highway projects but will also have to build 7000 km stretch every year. Experts say it seems unlikely unless the highway agency augments its capacity.
RP Singh, NHAI chairman, however, said, “Our target was to build 3000 km. Our achievement is much better than expected and is the highest as compared to the previous years”.
But more than meeting its construction target, what has worried road ministry officials is the dismal achievement vis a vis awarding highway projects during 2012-13. The NHAI has been able to award a little over 1,000 km stretch as on March 31 as against the original target of 9,500 km which was later scaled down to 6600 km.
Officials attribute this to a host of factors, including the prevailing market condition and delay in getting environment clearance. “For the time being, we should live with this. There are a number of reasons — administrative such as delay in getting environment clearance, land acquisition etc. and market related which have been responsible for dismal award figures,” BK Chaturvedi, Planning Commission member (infrastructure) told HT.
While NHAI has been able to build 2900 km highways during 2012-13, the road ministry has been able to build an additional 2900 km as part of its various non national highway development projects.
Source- http://paper.hindustantimes.com
These include providing connectivity to the naxal-affected areas and the North-East region.
Chaturvedi is holding a meeting to review the progress of road projects on April 3.
NHAI project award touches new low of 787 km in FY13
March 26, 2013
Financial Express reported that the National Highways Authority of India has reached a new low in project awards, managing only 787 km in 2012 to 13 a level last seen in 2008 to 09 when the global economy witnessed its worst ever slowdown.
The global slowdown following the sub prime crisis in the United States had its effect on NHAI’s performance, which could award only 6 projects spanning 600 km.
The dismal performance during the current year in terms of project awards was preceded by high performance in 2011 to 12 when the NHAI and the highways ministry together had awarded a record 8,000 km of projects. Of that, around 6,000 km were awarded by NHAI and the rest by the road transport ministry.
Officials in NHAI said that their board is likely to take up the proposal for another 500 km of road projects in its meeting to be held on Tuesday. But it will be difficult for the highways authority to be able to complete the award of projects before the end of this fiscal.
Low award by NHAI will badly impact the government’s truncated target of awarding 5,000 km for road projects in the current year.
After a robust performance in 2011 to 12 the Budget set a target of 8,800 km of road projects for 2012 to 13 which was later increased to 9,500 km by Prime Minister Mr Manmohan Singh. Mid way the target was further revised downwards to 8,500 km and further down to 5,000 km which is unlikely to be achieved.
NHAI together with the road transport ministry will likely be able to award 2,300
Source: http://www.steelguru.com
8 projects operational, co may securitise assets: Sadbhav
March 25, 2013
Nitin Patel, ED, Sadbhav Engineering , says that recently the company as emerged as a successful bidder for the two lane project in Tamil Nadu. The project is based on annuity basis. The company has also submitted another bid for Rohtak-Hissar project for Rs 1300 crore, the results for which is expected today evening.
Out of the 12 projects, 8 projects are now operational and the company expects the ninth project to be operational by June. Going forward, depending on the equity and investment commitment the company may go for asset securitization.
Below is the edited transcript of his interview to CNBC-TV18.
Q: It is understood that your company has emerged as a successful bidder in NHAI’s two lane Tamil Nadu project. By when do you plan to start construction on the project? What will be the total cost and your profit margins?
A: This is a two lane road project based on annuity. The existing highway has width of seven meter which needs to be extended to 10 meter and the length of the project is 80 kilometers. We estimate the total project cost to be around Rs 400 crore and it will take around two years to complete the job. We have received a concession period of 15 years. So, for the remaining 13 years we will receive annuity amount from NHAI as per the terms of concession.
Q: How much margins do you make upfront?
A: In normal course, we expect to make around 12-13 percent at EBITDA level at EPC value and around 16-18 percent as returns on investment. This is the normal bidding criteria for us.
Q: What has been the activity from NHAI side on both build-operate-transfer (BOT) and EPC. How does the order pipeline looks? Are they looking aggressive in awarding orders?
A: On cash contract front, NHAI invited around 8-9 tenders during last month. The response was quite good and NHAI received bidders at almost 20-22 percent lower then their estimate cost on the cash contract front. On BOT front, only one tender went to IL&FS Transportation Networks (India) Limited (ITNL) which is of Barwa Adda to Panghat.
We have received annuity for the second project. Today, we have submitted a bid for Rohtak-Hissar project for Rs 1300 crore, the results is expected to be out by today evening. Five entities have submitted their bid including us. Another 2-3 bids will be submitted before March 31, the central government and the Planning Commission will give approval for rates for the projects. Later, based on that, NHAI will come for the bidding and particularly in BOT and annuity front.
Q: Do you have any plans to reduce debt, are you securitizing any project, your debt stands at over Rs 3000 crore?
A: Out of the 12 projects that the company has, 8 are now operational and we expect the ninth project to be operational by June. So, in terms of the operational projects the number of projects is high and also the revenue parameter seems reasonable.
So, based on our requirement of the equity and investment commitment we will plan to securitise one or two assets. We have started that process but we require equity investment over the period four years from now so the planning will be done as and when needed.
source: http://www.moneycontrol.com
PBA Infra bags EPC contract from Solapur Tollways
March 11, 2013
Lalitha Rao ,Monday, March 11, 2013
PBA Infrastructure Ltd has been awarded the EPC contract for four laning the Solapur-Gulbarga, Maharashtra- Karnataka border section of National Highway 9, from Solapur Tollways Pvt Ltd, a joint venture of Coastal-Srei Consortium. The contract worth 780 crore is being executed as BOT (Toll) on DBFOT pattern under National Highways Development Project Phase-III. NHAI had appointed Artefact Projects Ltd as project consultant.
The Cabinet Committee of Infrastructure approved the project in November 2011 at a total estimated cost of992 crore including land acquisition, rehabilitation and pre-construction activities. The concession period including construction period of the project is 25 years. The project starting from km 249.00 to km 348.80 would cover the districts of Pune, Solapur and Osmanabad in Maharashtra.
Speaking to Projectmonitor, S.K. Bothra, President, PBA Infrastructure Ltd, said, “We are mobilsing fund through five banks with Canara Bank as the leading Bank. We are planning to start the work by April 15.”
While talking on the land details he said that about 80 per cent of the land has been possessed and the remaining stretch would be acquired soon. The four laning of the 100-km long stretch is expected to be completed in 36 months, he said.
Srei Infrastructure Pvt Ltd, the first beneficiary of the project, under consortium arrangements with various companies has a diversified portfolio of annuity and toll-based road projects close to 5,500 km with a total capital cost of around 13,000 crore, awarded by the NHAI under NHDP, Ministry of Road Transport and Highways and various other State Governments.
In its 2011-2012 Annual report, the company stated that during the year under review, the Company as co-developer has successfully completed the construction of Thrissur-Angamali Road Project in Kerala on NH-47 under NHAI and Jaora Nayagaon Road Project in Madhya Pradesh on SH-31 under Madhya Pradesh Road Development Corporation. Meanwhile, the company also started the six-laning of Chandikhole Jagatpur Bhubaneswar project in Odisha on NH-5 under NHAI. Other than the Solapur- Maharashtra Karnataka Border project on NH-9 the company also won the Bikaner-Suratgarh project on NH-15 from Public Works Department of Rajasthan on build- operate transfer basis.
Source-http://www.projectsmonitor.com
GMR exits NHAI project in frustration over red tape
December 29, 2012
According to Arun Bhagat, EVP and group head – corporate communications, GMR Group, “This is a 555 km-long, 4-6 laning of the Kishangarh- Udaipur- Ahmedabad stretch.”
“We were awarded this in September 2011. At the end of about 16 months since the award of contract, certain critical permissions that were applied for were yet to be granted,” he clarified.
“Despite doing whatever was required, the permissions were not granted and this forced us to serve a termination notice under terms of the contract.”Source: moneycontrol.com
India Inc shuns govt road projects
December 24, 2012
MUMBAI: The infra growth story at least in the road sector appears to be over as the private sector is now shunning government’s road projects. The government which announced an ambitious target of $1 trillion of infrastructure spending is finding no takers for the 8,000 km of road projects to be awarded under the built, operate & transfer (BOT) mechanism this fiscal.
Interestingly, the National Highways Authority of India (NHAI), the nodal agency for awarding these road projects, witnessed phenomenal success in awarding over 8,000 km of road projects last year as 31 of the 51 road project were bagged at premium. Based on last year’s success, the government increased the target to award 8,800 kms of road projects this year; however, NHAI so far was able to award only 700 kms with less than four months remaining in the current fiscal.
Two projects, worth about Rs 2,450 crore, awarded last year to DSC Ltd and Gannon-Dunkerley Co Ltd were terminated after failure to achieve financial closure. This was the first time that such termination had to be done due to failure of companies to achieve financial closure (tie up debt).
At current pace of less than 5 km of road construction per day, the government is way behind its ambitious target of achieving 20 km of road construction per day for which it needs to award over 7,000 km of road projects each year. The reason: Availability of 50 road projects worth Rs 50,000 crore totaling 5,000 km are on the block in the secondary market as the debt-laden infrastructure firms wants to get rid of these road projects that they bagged by aggressive bidding and are now finding it difficult to execute due to the depressed returns. Prime Minister Manmohan Singh reviewed the performance of the transport sector in a series of meetings recently and a recent PMO statement on targets for awarding road transport and highways project last week said, “The ministry will try its best to award road projects as per the original targets for FY 12-13 and will certainly cross 8,000 kms of awards this year by March, 2013. Road projects of at least 3,000 kms length will be awarded under OMT by March, 2013.”
This means that in the absence of takers for road projects under BOT basis, which requires companies to raise funds from the market, the government is planning to award 3,000 km of road projects on engineering procurement contract (EPC) basis, where government spends the entire money required to build roads. However a government statement on Wednesday said, “As against the target for awarding works for a total length of 8,800 km during 2012-13, it has been possible to award projects for a length of 705 km upto October, 2012. Some projects have not received good response from bidders. Apart from general slowdown of economy, viability of some of the projects, sectoral lending caps of the banks, limitations of the concessionaires like availability of equity and other resources to execute the projects appear to be the main factors for poor response.”
“I have my doubts on the PMO statement. If they awarded just 700 kms in the first nine months, then how can they award 9000 km in the next three months. The constraints like land acquisition, funding from banks and remain the same. The government first needs to address these issues before awarding further road projects,” Bajrang Choudhary, CEO, Infrastructure Project Development at SREI Infra told ToI. Leading infrastructure firms like L&T, GVK, GMR, IVRCL, Gammon Infrastructure, SREI Infrastructure, Gayatri Projects, Madhucon Projects, Ashoka Buildcon amongst others have meanwhile reportedly put their road assets on the block.
Infra firms meanwhile are being chased by their lenders to sell assets any which way they can as the banks have stopped lending to the road sector with stringent lending norms scaring away private developers from investing in the highway projects. Over three dozen highway projects are awaiting financial closure.
source: http://timesofindia.indiatimes.com
Govt may miss road award target
October 15, 2012
NEW DELHI: Private highway developers, who are struggling to get finances for projects, are likely to impact government’s target of awarding 9,500 km during this fiscal. With only 600-odd km road stretches awarded during the first half of the financial year, now even senior National Highways Authority of India (NHAI) officials are conceding that they can award not more than 5,000 km till March, 2013.
At least 23 road projects awarded last year have missed their timeline to tie up funds. NHAI gives six months to contractors to get funds from banks and financial institutions for all build, operate and transfer (BOT) projects.