Road min downs shutters on new projects till Nov
July 30, 2013
TIMSY JAIPURIA : NEW DELHI, JUL 25, 2013,
At a time when the Prime Minister’s Office (PMO) has stepped up tracking the progress in award and implementation of infrastructure projects, the road ministry and the National Highways Authority of India (NHAI) have decided not to award any new highway projects until November.
The reason: financial stress at potential bidders, non-availability of land and uncertainty over securing environment clearances. The virtual suspension of bidding follows a steep decline in award of new projects. Awards of build-operate-transfer (BOT) highway projects which had peaked in 2011-12 at 6,491 km saw a dramatic decline to 1,116 km in 2012-13. This year, clearly, is going to be worse.
Government sources and officials from developers like Soma Enterprises and Reliance Infrastructure separately confirmed to FE that no new projects were likely to be awarded till close to the end of 2013. “The bull run in the highway sector is over. There are no takers for any new road projects,” said DV Raju, vice-president, National Highway Builders Federation.
A senior NHAI official said: “We are not ready to launch any bid on the engineering procurement and construction (EPC) mode nor the BOT mode as of now. Developers are cash-strapped and the investment climate is not conducive enough. We don’t want to launch bids in a hurry in a bad market.”
Developers feel the government must prepare detailed project reports and traffic studies to attract the right bidders and take steps to prevent long-pending arbitration cases, high interest rates and falling toll collections hindering projects.
“The market scenario is not good. Highway developers have had several communications with the roads ministry and the NHAI has highlighted the problems faced by developers.
Land acquisition and banks’ reluctance to lend are major concerns. Until these issue are resolved, the highways sector is unlikely to look up,” Sudhir Hoshing, CEO Reliance Infrastructure said. Government sources, however, said the authorities would ensure that developers do not face problems and address their concerns at the earliest. The government is disturbed by rising incidents of developers unable to achieve financial closure and walking away from contracts. NHAI has been encouraging builders not to abandon projects and complete the contracts, these sources said.
“We are working towards organising the back-end work including minimum of 80% of land acquisition and environment and mining clearances. Until we meet all necessary requirements, we won’t be in a position to award any new project either on EPC mode or the BOT mode until October-November,” the a road ministry official quoted earlier said.
Source-http://www.financialexpress.com
Hoping stalled projects will revive on policy tweaks: NHAI
June 21, 2013
The year 2012-13 was one of the most challenging years in terms of awarding of projects, says National Highways Authority of India (NHAI) chairman RP Singh.
RP Singh)
Chairman
NHAI
The year 2012-13 was one of the most challenging years in terms of awarding of projects, says National Highways Authority of India (NHAI) chairman RP Singh.
The original target of awarding 8,800 km was increased to 9,500 km by PMO mid-year; the target was lowered to 8,500 km and then to 5,000 km. However, NHAI ended up awarding 1,000-1,100 km. The poor performance was on a high base and construction per day was down from 16 km per day to approx 10-12 km per day.
Singh says award of projects is a market-driven phenomenon, adding that the NHAI is now looking to award projects only on EPC basis versus BoT as most developers do not want to bid for the latter due to funding constraints.
Banks are holding their funds towards the roads sector until assured of design and traffic growth details. NHAI believes the Indian road sector needs to get private equity players, along with other ways to pay premium. “We do not see NHAI taking up too many cash contract projects,” he told CNBC-TV18 in an interview.
However, in a major relief to the road development sector, the Supreme Court on March 12, 2013 ruled in favour of the NHAI by delinking the environment clearance (EC) and the forest clearance (FC). Now, the contracting companies do not have to wait for the FC and can commence the construction work once the EC is received. This will allow projects to get completed faster, Singh believes.
The work on 20 stalled highway projects worth Rs 27,000 crore, which were stuck for a long time for want of EC, would be executed soon after the clearance from the Ministry of Environment and Forests (MoEF) and the projects are set to get back on track.
Meanwhile, the government has asked banks to ease funding for the road projects and consider toll revenues as tangible assets. The finance ministry has proposed RBI to treat loans to the roads project as secured. NHAI says if government’s proposals are implemented, credit flows to the fund-starved sector could grow by at least 20-25 percent. The road ministry has been making a lot of representations to the Finmin lately to discuss sector issues.
On GMR exiting Rs 7,700 crore Ahmedabad- Kishangarh highway project, and GVK exiting the Shivpuri-Dewas Expressway in MP, Singh says NHAI is working out details to back-end premiums for GMR and GVK projects. “The companies exited the high profile projects as they turned unviable for them,” he says. GMR, however, had indicated fresh interest in the project if the premium terms are tweaked.
Spadework for renovation of NH-143 finally begins
June 21, 2013
By Express News Service – ROURKELA
National Highways Authority of India (NHAI) has finally started the spadework for widening NH-143 (earlier NH-23) stretch from Birmitrapur to Barkote passing through Sundargarh and Deogarh districts.
NHAI sources said of the total 125.615 km of the NH, the stretch of around 88 km between Birmitrapur and Rajamunda would be converted into four-lane while the rest stretch till Barkote would be two-lane with ‘paved shoulders’.
The NHAI under the National Highway Development Project (NHDP) Phase-IV has allocated `778.60 crore for the project. It would be executed by the Birmitrapur-Barkote Tollway Ltd (BBTL) which has been appointed by principal construction firm Gammon Infrastructure Project Ltd on design, build, finance, operate and transfer (DBFOT) basis. The BBTL submitted a design to the NHAI a couple of days back.
The project includes a new Brahmani bridge at Panposh to replace the existing rickety one. Manager (Technical), NHAI, Madan Mohan Sahu said the bridge will be located between the existing bridge and the railway-over-bridge at Panposh to minimise displacement. There would be bypasses at Birmitrapur, Kuanrmunda and Lathikata while at Rajamunda there would be a rotary. Once they get the land and forest clearance, the project could be completed in 30 months, Sahu said.
Following a review meeting, Sundargarh Collector Roopa Roshan Sahoo appointed Rourkela ADM RN Mishra as the authority to acquire land. The Collector said all technical issues are being sorted out on priority basis.
The ADM informed that the notification for the bridge area under the provision of the NHAI Act has been done and the required notification for rest areas would be done by June 16.
Counting of trees between Rourkela and Rajamunda to be felled for the highway project has been completed and the process towards Birmitrapur is pending.
Administrative sources apprehend that acquisition of forest land may delay the project as the Highway passes through several reserve forests under the Rourkela and Bonai forest divisions in the district. Rajgangpur MLA Gregory Minz who raised the issue several times insisted on timely completion of the project.
Source-http://newindianexpress.com/
Road Ministry to take up GMR Infra project issue with Committee of Secretaries
June 19, 2013
By PTI |
NEW DELHI: In a bid to salvage the stalled Kishangarh-Udaipur-Ahmedabad highway project of GMR Infrastructure, the Ministry of Road Transport and Highways will soon approach the Committee of Secretaries for the matter.
Sachin bridge to make twin-city concept a reality
June 19, 2013
Himansshu Bhatt, TNN |
SURAT: The 700-metre-long rail overbridge atSachin on Surat-Navsari Road is now ready after one-year delay. The work on the two-laneoverbridge had started four years ago. This bridge, built at a cost of Rs 18 crore, will cater to over 20,000 per car units (PCU) and 5,000 commercial vehicles per day (CVD).
Road trips take a toll on drivers
June 17, 2013
Koride Mahesh, TNN |
Except the Karimnagar highway, where toll collection is yet to begin, motorists on all other highways, including the Hyderabad-Vijayawada NH 65, Hyderabad-Nagpur NH 44, Hyderabad-Bangalore, Hyderabad-Warangal NH 202 and Miyapur-Sangareddy highway have to pay taxes. Apart from that, the Hyderabad Metropolitan Development Authority (HMDA) has been collecting toll on the completed stretches of the Outer Ring Road (ORR) and on the road to the Rajiv Gandhi International Airport at Shamshabad.
The toll being collected on the highways ranges from Rs 1.20 to Rs 2 per kilometre depending on the cost of the project. For example, motorists have to shell out Rs 75 at the toll plaza at Gudur village near Bibinagar for a mere 35 km stretch from Hyderabad to Yadagiri.
The developers are also increasing the toll every six months citing conditions in the agreement. For instance, the Hyderabad-Yadagiri Tollways Pvt Ltd started collecting tax on the NH 202 to Warangal barely six months ago in December 2012. But the developer decided to increase the toll amount from June 11 midnight without even waiting for clearance from the NHAI.
“The hike in toll has not been cleared by the NHAI but the developer decided to increase the tax anyway. We will ask them to wait till it is cleared by the authority,” P Ramesh Reddy, project director of Hyderabad Project Implementation Unit of NHAI, told STOI.
Even APSRTC buses are being subjected to the tax ranging from Rs 4 to Rs 6 per km. With the increasing burden, the corporation recently decided to pass on the toll burden to the passengers. “Both the state and Centre have given up on road development works and have handed them over to private developers under the Build Operate and Transfer (BOT) mode. But the burden is being borne by the general public,” lamented B Giridhar, a software employee and resident of Madhuranagar.
Hi-tech traffic signals in Bhubaneshwar await green light
June 17, 2013
Riyan Ramanath V, TNN |
The Bhubaneswar Municipal Corporation (BMC) has roped in a private party to install upgraded signals called Intelligent Traffic System (ITS) on a build-operate-transfer (BOT) basis for 10 years. The private party, Stanpower, a Hyderabad-based company, known for its innovative technology applications, is likely to give a presentation on ITS to traffic and BMC officials next week. The BOT will facilitate the BMC to have full rights over the assets after 10 years. The company will only get advertisement rights and the cost of operation during the period.
The new system can assist traffic authorities in maximizing the operational efficiency of the signals, said BMC commissioner Sanjib Mishra. “ITS will help ease the traffic flow, reducing delays and fuel consumption of vehicles. It will also help monitor air and noise pollution,” said the commissioner. The ITS uses technology such as CCTV camera-linked traffic controllers and central operation centres, where the computers analyse the traffic flow and disseminate traffic management information, added the commissioner.
At present, the city has about 60 traffic posts of which 20 have signals, which can be operated both manually and automatically. However, human intervention is still required to monitor the violators. “At times we fail to penalize the violators as we have to run after them. Once the technology is installed, we can penalize the commuters later as the CCTVs will capture the registration number of violating vehicles,” said traffic ACP Binod Das.
The commissioner has written to Bhubaneswar DCP, National Highways Authority of India (NHAI), regional transport officers and chief engineer of roads seeking their cooperation to adopt the system in the city. “If the stakeholders are convinced about the benefits of launching the technology in Bhubaneswar, the company will be given the go-ahead,” said the commissioner.
“The traffic management in urban set-up has undergone many changes. It is no more limited to flashing of lights at intersections. Present system can’t monitor red light jumping and speed of vehicles. Secondly, there is human intervention while tracking the violators, who don’t wear helmets and drive without fastening seat belts. In many cities, the violations are documented by the technology,” said urban planer P R Rout.
“The ITS technology is so sophisticated that it is able to detect any solid object near traffic posts. The system runs through a central server, which can maintain the database of all traffic signals of the city,” said a BMC official .
Centre will soon allow 100% stake in BOT projects
May 20, 2013
Infrastructure developer IVRCL Limited is going slow on its proposal to monetise three more build, operate and transfer projects in the light of expectations that the Union government will soon take a decision to allow 100 per cent stake sale in BOT projects. “It is just a matter of procedure. The decision will come soon as everybody, including the NHAI (National Highways Authority of India), is in favour of it,” IVRCL chairman and managing director, E Sudhir Reddy, told Business Standard. At present, the Centre allows only 74 per cent stake sale in BOT projects.
Reddy said IVRCL would expedite the process of selling more projects after Centre’s decision in this regard. The Hyderabad-based company recently sold three BOT projects – Salem Tollway, Kumarapalayam Tollway and IVRCL Chengapally Tollway – to the Tata group firm TRIL Roads Private Limited. The stake sale is yet to be approved by the NHAI and institutional lenders. The projects have been reportedly executed at a cost of Rs 2,200 crore and nearly two-thirds of this money had been lent by banks.
Reddy, however, said banks approving the stake sale should not be a problem as the projects were sold to a Tata group company, which has a good standing among the financial institutions. Last month, industry sources said, some of the operators of BOT projects hailing from Andhra Pradesh met the Prime Minister and apprised him of their problems.
More than the high interest rates, they were said to have told the Prime Minister that the rising cost of construction material due to sudden policy changes by state government was making development of BOT projects unviable.For instance, Reddy said, IVRCL was now securing sand from Jharkhand to execute a BOT project in Bihar as the Bihar government had banned sand mining in the state. There was also cost escalation on account of state governments delaying in execution of state-support agreement. These along with other factors were resulting in project costs spiralling by almost 15-20 per cent over the original estimates.
Besides, the developers had tendered for BOT projects assuming the GDP growth rate would be in double digits. With no such thing happening, only 5 per cent of the BOT projects in the country was now stated to be profitable.
Road minister calls for faster land acquisition
May 17, 2013
Road Transport and Highways Minister C P Joshi said there is a need to streamline the land acquisition process in order to fast-track road projects by NHAI and state agencies. The Minister said this while reviewing the status of land acquisition for National Highways Development Project and also other road construction programmes.
Source-http://constructionsphere.com
Govt’s pre-fixation with PPP not good for infrastructure: Parliamentary Panel
May 10, 2013
PTI : New Delhi, Sun May 05 2013,
Urging the government to come out of “pathological prefixation” with public-private-partnership (PPP) model, a Parliamentary panel has asked it to build through budgetary support all highways where bidders have failed to respond.
“PPP as a model for the development of road project needs to be reviewed seriously in the light of our experience so far in this regard. That private capital is mainly for profit is borne out by the fact that the profitable projects are being bid out fast,” Standing Committee on Transport, Tourism and Culture has said in its latest report.
Committee Chairman and CPI-M MP Sitaram Yechury said: “Unfortunately the government has pathological pre-fixation with PPP which is hindering infrastructure development in the country as driven by the objective of profit, private sector is not coming forward to bid for unprofitable projects.”
Stressing upon the need for government’s thrust on infrastructure Yechury said: “No other country whether USA or China depended on private sector for building its infrastructure unlike India. Unfortunately the allocation has been reduced drastically for infrastructure as Planning Commission is encouraging private partnership.”
He said only such projects were bid out in the PPP mode where profit is envisaged, asking as to how there was no response for 13 bids invited by the NHAI last year. The report said that a vast country like India needed faster connectivity to its length and breadth and should “adopt an alternative model of project development which is development driven and not profit driven”.
It added: “Since profitable projects are sold out first, the government is facing problems in getting bidders for such non-profitable road projects as those in Left Wing Extremist and North-East Areas.”
Emphasising that India needs faster construction of roads, the Committee recommended that “all such projects without bidders should be developed with the budgetary support from the government and the Planning Commission needs to be more practical and careful about its role and function”. National Highways Authority of India (NHAI) had set a target to award projects for 7,464 km of roads during the last financial year, of which only projects worth 879 km could be awarded.
Source – http://www.indianexpress.com