CCEA approves 4-laning of Dimapur-Kohima highway in Nagaland

June 19, 2013

 

(The government on Thursday approved the 4-laning of Dimapur-Kohima National Highway in Nagaland at a total cost of Rs 1,089.87 crore.) 

NEW DELHI: The government on Thursday approved the 4-laning of Dimapur-Kohima National Highway in  Nagaland at a total cost of Rs 1,089.87 crore.”The Cabinet Committee on Economic Affairs today approved the implementation of the project of 4-laning of the Dimapur-Kohima section from 124.1 km to 172.9 km of NH-39,” Finance Minister P Chidambaram said at a press briefing.

This project is under the special Accelerated Road Development Programme (SARDP-NE) in North Eastern Region, he said.

The total length of the road will be 42.8 km with total project cost of Rs 1,089.87 crore (excluding land acquisition and pre-construction).

The concessionaire will make all expenditure to complete the project and will charge the annuity from the Government.

“The main object of the project is to expedite the improvement of infrastructure in Nagaland. It will facilitate reducing the time and cost of travel for traffic playing between Dimapur to Kohima. It will also increase the potential of employment to local labourers for project activities,” he said.

This project was delayed due to delay in land acquisition process in the state.

At present, Nagaland has 494 km of National Highways.

Source-http://economictimes.indiatimes.com

 

 

 

 

Road Ministry to approach CoS on GMR highway project in 2 weeks

June 19, 2013

By PTI

NEW DELHI: The Road Transport Ministry will approach the Committee of Secretaries for an amicable way out for the Kishangarh-Ahmedabad Highway project which is stalled after GMR’s exit.GMR Infrastructure BSE 0.50 % early this year had walked out of the project citing difficulties in taking up the project due to regulatory hurdles, including delays in environment clearance and land acquisition.

According to sources, GMR Infrastructure was ready to restart the project with some preconditions, including making piece-meal payments.

The Law Ministry, however, had already rejected the developer’s preconditions, including piece-meal payments, for resuming work on the project.

“We are going to the Committee of Secretaries (CoS) on the matter,” Road Secretary Vijar Chibber told reporters here. He said the meeting of CoS may take place in the next 10-15 days. The CoS is headed by Cabinet Secretary Ajit Kumar Seth.

The company has also said it would pay about 50 per cent of the amount to restart the work on project at present and pay the remaining sum including interest in subsequent years.

The Ministry and the company are already in discussions to rescue the project.

Sources added that the proposal from the Ministry is to ask the company to make requisite payments in time and to seek its guarantee to ensure that the project is not abandoned mid-way, leading to financial burden falling on government.

The project is estimated to have required an investment of Rs 5,387 crore. The Bangalore-based group had won the project in western India through international competitive bidding in September 2011 at Rs 636 crore annual premium for 26 years.

NHAI had said that the company exited the project on account of financial hurdles in arranging finance for the project and not due to lack of regulatory clearances.

It is to be implemented through the Public Private Partnership (PPP) model on Design, Build, Finance, Operate and Transfer basis.

 

Source-http://economictimes.indiatimes.com

 

Road Ministry to take up GMR Infra project issue with Committee of Secretaries

June 19, 2013

By PTI |

GMR Infrastructure was ready to start the project with some preconditions, including making piece-meal payments.

(GMR Infrastructure was ready to start the project with some preconditions, including making piece-meal payments.)

 

 

 

 

NEW DELHI: In a bid to salvage the stalled Kishangarh-Udaipur-Ahmedabad highway project of GMR Infrastructure, the Ministry of Road Transport and Highways will soon approach the Committee of Secretaries for the matter.

“The matter will go to the Committee of Secretaries, we want that the net present value of the project does not change,” a Road Ministry official told reporters.The difference between the present value of cash inflows and the present value of cash outflows is the net present value of a project.
The Ministry and the company are already in discussions to rescue the project.According to sources, GMR Infrastructure BSE 0.76 % was ready to start the project with some preconditions, including making piece-meal payments.The company has also said it would pay about 50 per cent of the amount to restart the work on project at present and pay the remaining sum in the subsequent years, including interest.The official added that the proposal from the Ministry is to ask the company to make the requisite payments in time and to seek its guarantee to ensure that the project is not abandoned mid-way, leading to the financial burden falling on the the government.
Earlier this year, GMR Infrastructure walked out of the Kishangarh-Udaipur-Ahmedabad project 16 months after securing the order.The project is estimated to have required an investment of Rs 5,387 crore. The Bangalore-based group had won the project in western India through international competitive bidding at Rs 636 crore annual premium for 26 years.It is believed that the company terminated the contract on account of difficulties in taking up the project due to regulatory hurdles, including delays in environment clearance and land acquisition.However, NHAI had said that the company exited the project on account of financial hurdles in arranging finance for the project and not due to lack of regulatory clearances.The company had won the project in September, 2011, through the international competitive bidding route. It is to be implemented through the Public Private Partnership (PPP) model on Design, Build, Finance, Operate and Transfer basis.
Source-http://economictimes.indiatimes.com

Kundli-Manesar-Palwal expressway likely to miss May 31 deadline

June 19, 2013

 

Aditya Dev, TNN | May 27, 2013, 02.18 AM IST

GURGAON: The Kundli-Manesar-Palwal (KMP) expressway is likely to miss the deadline of May 31, 2013 set for completing the entire 135-km project. So far the overall physical progress for the project is about 70%, even as the priority stretch between Manesar and Palwal is 85% complete. While HSIIDC says there is no such legitimate impediments exists as on today, the concessionaire, DSC Ltd, claims unavailability of land as well as delay in approvals to implement change of scope for not completing the project on time.
Surprisingly, there has been no change in the stance of the concessionaire since last year as far as the physical progress of the project, whether it is the entire stretch or the priority stretch, is concerned. The concessionaire has been quoting the same figures of 70% and 85% for the entire project and the priority stretch respectively for the last one year.

The information received under an RTI application revealed that between January and March 2013, the project made a meager 0.17% progress. In fact, collating this information with another RTI reply reveals the apathy of the concessionaire in completing the project. The KMP project has made a dismal 1.2% physical progress between June, 2012 and March 2013. Likewise, it had made just 4.46% during the year between July 2011 and July 2012.

This information has been revealed in the RTI replies to a Gurgaon resident, Aseem Takyar, an RTI activist. Takyar has asked HSIIDC to provide monthly completion report of the project.

Another important query was the estimated time for the completion of the entire project. HSIIDC replied that as per the assurance given by the concessionaire, the project will be completed by May 31 2013.

However, when contacted, a spokesperson for KMP Expressways Ltd, gave various reasons for the slow progress of the project. The KMP expressway Ltd is the concessionaire of which DSC Ltd is the main partner.

The concessionaire had made the commitment at a meeting in Delhi on June 8, 2012 between chief ministers of Haryana and Delhi, to open the Manesar-Palwal section for tolling within the next 90 to 120 days and complete the expressway by May 31, 2013.

The overall physical progress for the entire project is about 70%. The approvals for the change of scope claims are still awaited and funds are yet to be released to the concessionaire which is causing some delay in the project. Regarding this issue, the arbitration clause has been invoked so that there can be a speedy agreement on the amount of funds payable to the concessionaire due to the change of scope of the project. A fast track Arbitration Settlement could actually help in the progress of the project, informed the spokesperson.

There have been a lot of design changes in major and minor structures directed by the client which has led to the change of scope of work. We have provided the full detailed break-up of the change of scope work along with the costs to the client for approval, added the spokesperson.

For the delay in completion of the Manesar-Palwal stretch, the spokesperson said the work had been held up because there is a section of around a km in the Nuh area where the road is still to be built as the land around that area has not yet been handed over to us free of encumbrances. Once this land is made available to us, we would need about three months to build the road on this section and lay the top layer for the entire priority stretch and complete it.

The HSIIDC has been made executing agency for developing the Kundli-Manesar Palwal Expressway (Western Peripheral Expressway around Delhi) by the Haryana government. The expressway is being developed on build-operate-transfer (BOT) and zero-grant basis, with a concession period of 23 years and nine months, including three years of construction period. The date of start of the project was July 31, 2006. The scheduled date of completion of construction was July 29, 2009.

The project involves construction of 47 underpasses, 31 cattle crossings, 61 pedestrian crossings, 33 agriculture vehicles overpasses, 26 bridges, 4 railway overbridges and 3 grade separators at NH 1, NH 10 and NH 8. The project would allow heavy and commercial vehicles to completely bypass the Delhi NCR region thereby decongesting traffic within the capital.

Source-http://timesofindia.indiatimes.com

 

Akurdi railway underbridge to be opened partially

June 19, 2013

TNN |

PUNE: The Pimpri Chinchwad New Township Development Authority (PCNTDA) will open one side of the railway underbridge being built nearAkurdi railway station for vehicular traffic and pedestrians within a week.Chief executive officer of PCNTDA Yogesh Mhasesaid the old underbridge gets waterlogged in the monsoon causing disruption in vehicular traffic. So authorities have planned to open one side of the under construction underbridge to provide some relief to commuters and pedestrians.

The contractors have been asked to complete work on the approach road. The old underbridge near the railway station links Ravet, Kiwale, Walhekarwadi and other areas like the old Pune-Mumbai highway and Nigdi-Pradhikaran.

The work order for the new project, to be built at a cost of Rs 8.10 crore, was given in May 2010. The work was to be completed in 15 months, but is still incomplete.

 

Sachin bridge to make twin-city concept a reality

June 19, 2013

Himansshu Bhatt, TNN |

SURAT: The 700-metre-long rail overbridge atSachin on Surat-Navsari Road is now ready after one-year delay. The work on the two-laneoverbridge had started four years ago. This bridge, built at a cost of Rs 18 crore, will cater to over 20,000 per car units (PCU) and 5,000 commercial vehicles per day (CVD).

The bridge is expected to play a significant role in the development of Surat and Navsari as twin cities in the future. It will reduce travel time by 40 minutes from Udhna-Surat to Navsari town in a car. The lanes of the bridge are 30 and 28 metre wide.Surat Urban Development Authority (SUDA) executive engineer PI Patel, said, “The bridge was to be ready by June 2012, but due to some unavoidable circumstances it could not be.”The bridge is located halfway between Surat and Navsari. “The bridge will be a major junction for heavy vehicular traffic on way to Hajira from National Highway 8. These vehicles coming from Mumbai or Ahmedabad need not enter Surat city,” Patel said.
The National Highway Authority (NHA) is building a six-lane bridge next to this rail overbridge that connects Palsana to Hajira. One lane has been completed so far. This infrastructure development is central to overall development of the proposed freight corridor of Surat-Hajira When Surat-Navsari twin cities become a reality in 2026 with a population of 1.20 crore, this ROB will bear the maximum burden of traffic going to and from Surat to Navsari. In the next five years, the vehicular traffic is likely to double.The ROB has been built from the funds sanctioned under the Jawaharlal Nehru National Urban Renewal Mission (JnNURM). It would be dedicated to the people by this month-end

The bicycle diaries: These residents drive home the green message

June 18, 2013

Hindustan Times  Gurgaon,

(Over 250 cyclists comprising of government officials, students, teachers, cycling enthusiasts and civic groups converged in Gurgaon to make the city bike-friendly. Students, government officials, teachers, cycling enthusiasts, civic groups cycled to create awareness about alternative transport systems.The Non-Motorised Transport group organised a ‘Walk to Work’ campaign in association with NASSCOM, in Gurgaon, India. HT photo/Manoj Kumar -HT Photo/Manoj Kumar)

 

For a city that is synonymous with expressways, high-end vehicles and fatal accidents, the idea of a dedicated cycle track was unheard of till some time back.

But that was before a quaint group of enlightened residents had joined hands to form a Non-Motorised Transport (NMT) group.

The group has been instrumental in urging the Haryana Urban Development Authority (Huda) to work on a comprehensive NMT plan for Gurgaon with dedicated cycle and pedestrian tracks.

 It works with the vision to provide equitable road space to pedestrians, cyclists and other users in the Millennium City.

Since the latter half of 2011, this group has been conducting unique events to create a pedestrian and cyclists-friendly city.

The 500-member public group last month organised a unique ‘Walk to Work’ initiative in collaboration with industry body Nasscom where CEOs walked to their offices from the nearest Metro station instead of taking their cars.

“Thankfully, the NMT idea has now percolated into the minds of the city authorities. The city will set a positive example for the rest of the country if the plan gets the green signal,” Nisha Singh, a city councillor and one of the key group members.

The group also introduced Gurgaon to Columbia’s Ciclovia concept where roads are partly barricaded to stop the entry of motor vehicles so that cyclists and pedestrians can have a free and safe experience.

In an event in April at Leisure Valley Grounds, some of the most powerful men in Gurgaon — the Huda administrator, the municipal commissioner and the police commissioner – also took to the humble cycle.

Source-http://www.hindustantimes.com

 

 

 

 

 

 

 

   

 

 

 

.

 

 

SoBo skywalk to miss deadline

June 18, 2013

Saurabh Katkurwar, Hindustan Times  Mumbai, June 17, 2013

 The city’s most expensive skywalk, which is being constructed at Nana Chowk, has been delayed till August due to unfinished work pertaining to escalators and staircases. According to the latest deadline, the Maharashtra State Road Development Corporation Ltd (MSRDC) was supposed to open the 510-meter skywalk to the public in mid-June.

 

“Due to monsoon, some of the skywalk work is delayed. The remaining work is expected to finish in a month. The skywalk will be made open to people in August,” said MSRDC managing director Bipin Shrimali.

The original cost of the project was Rs39 crore when work commenced way back in 2008. As per the original deadline, the skywalk was supposed to be ready in June 2009. The cost has now escalated to Rs50.48 crore due to the four-year delay.

The oval-shaped skywalk, which is supported by 16 stress cables suspended from a central tower located at Nana Chowk, has three escalators and four staircases for its different arms. The MSRDC is yet to finish construction of these escalators and staircases.

“We are left with some work pertaining to escalators and elevators, which will be completed soon. In addition, finishing touches are being given to the skywalk,” said MSRDC chief engineer Subhash Nage.

Although the MSRDC claims that the skywalk will witness about 50,000 pedestrians daily, transport experts refute their claim. Transport expert Ajit Shenoy said: “The staircases and escalators have been built at the wrong locations — they are not in the direction of pedestrian flow. So commuters will not prefer to take the skywalk.”

Sourc-http://www.hindustantimes.com

Smartphones may replace Metro cards

June 18, 2013

Subhendu Ray, Hindustan Times  New Delhi, June 16, 2013

Travelling across the city in Delhi Metro is likely to get more comfortable if you are a smartphone user. You may not even need to carry a Metro smartcard or buy a token because your phone will have everything you need.The Delhi Metro Rail Corporation (DMRC) is exploring the possibility of introducing a new system termed near-field communication (NFC), which has the ability to make smartphones act as Metro smartcards. The NFC device in your phone will act as the electronic identity document and keycard.

“We hope to put the system in place soon and reduce the use of physical smartcards within two years before our network expansion under phase 3 is completed. NFC devices are currently at a trial stage,” said a senior engineer of the signalling department of DMRC.

http://www.hindustantimes.com/Images/Popup/2013/6/17_06_13-metro7.gif

The projected average daily metro ridership in 2016 is projected at nearly 40 lakh once phase 3 expansion is over. DMRC is eyeing at a 30 per cent reduction in manual smartphone transactions through this system.

Many new Samsung smartphones, Nokia Lumia phones, Sony’s Xperia range, HTC’s high-end phones and LG’s Optimus range support NFC. Many other smartphone makers too are reportedly keen on introducing the system.

“An antenna chip will be inserted in the smartphone, which will function as a smartcard. The commuter will have to bring the phone close to the automatic fare collection (AFC) gate to gain entry,” said Anuj Dayal, chief spokesperson of DMRC. The device will establish radio communication with the AFC gate when touched or in close proximity to the phone.

“The new generation phones will let you recharge the chip. The amount of recharge will be reflected in your monthly phone bills “, he added.

The NFC devices are also being tried as alternative to smartcards in Dubai and Singapore metros, he said.

 

Record no. of curves in ph-3 metro corridor

June 18, 2013

htreporters, Hindustan Times  New Delhi,

The Hazrat Nizamuddin-Shiv Vihar standard gauge corridor of the Delhi Metro, which is part of Phase III, will have a record number of sharp curves.”There are uneven twists and turns in this 25-km elevated corridor. So we have been forced to construct 14 curves on this stretch, which passes through highly congested areas of east Delhi such as Trilokpuri, Anand Vihar, Karkardooma, Welcome and Seelampur,” said a Delhi Metro spokesperson.

Curves with a radius between 200 and 300 meters are considered ‘sharp’ in urban rail construction. “The work on building sharp curves requires a great deal of engineering skills and several factors have to be kept in mind while designing special segments/spans at the turn concerned,” the spokesperson added.

The Hazrat Nizamuddin-Shiv Vihar corridor is a part of the 59-km-long Mukundpur-Shiv Vihar corridor.

Source-http://www.hindustantimes.com/

« Previous PageNext Page »